PMT 3.2 Assignment: Week 3 Exercises

Use the attached spreadsheet template to complete the assignment.  Click on each of the tabs in the template to view each of the exercises.  

Thanks

Ch 8 Ex 4

PMT472 3.2 ASSIGNMENT: WEEK 3 EXERCISES

CH. 8 EXERCISE 4

Given the network plan that follows, compute the early, late, and slack times. Using any approach you wish (e.g., trial and error), develop a loading chart for resource, electrical engineers (EE), and resource, mechanical engineers (ME).

Start
0
1

4

5

End

Legend

EE

EE

ME

ES
ID
EF

2

1

6

SL
Resource
SL

LS
DUR
LF

0
2

6

EE

ME

4

2

0
3

7

ME

EE

3

4

Loading Schedule

EE

ME

0
1
2
3
4
5
6
7
8
9
10
11
12

What is the project duration?

(Enter response)

Assume only one of each resource exists. Given your adjusted loading schedule, compute the early, late, and slack times for your project in the resource activity schedule.

Loading Schedule (adjusted for resource constraint)

EE

ME

0
1
2
3
4
5
6
7
8
9
10
11
12

Resource Activity Schedule (with resource constraint)

ID/RES
ES
LS
EF
LF
SL

1-EE

2-EE

3-ME

4-EE

5-ME

6-ME

7-EE

Which activities are now critical?

(Enter response)

What is the project duration now?

(Enter response)

Could something like this happen in real projects?

(Enter response)

Ch 9 Ex 1

PMT472 3.2 ASSIGNMENT: WEEK 3 EXERCISES

CH. 9 EXERCISE 1

Use the following information to compress one time unit per move using the least-cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity or activities were crashed and the adjusted total direct cost. Note: The correct normal project duration, critical path, and total direct cost are provided. The crash cost is how much extra it will cost to crash the activity per time unit reduced. The maximum crash time is how many time units the activity can be reduced by. E.g. Activity D can be reduced by 2 time units down to 1 time unit for a total additional cost of $120.

Activity
Crash Cost (slope)

Maximum Crash Time

Normal Time

Normal Cost

A
$50

1

3

$150

B
$100

1

3

$100

C
$60

2

4

$200

D
$60

2

3

$200

E
$70

1

4

$200

F
$0

0

1

$150

Crash Round 1

B

D

What was crashed:

Activity A was reduced by 1 day (or time unit) from 3 days to 2 days.

3

3

Adjusted total direct cost:

$1,050

A

F

The cheapest activity to reduce is A so we reduce it by its maximum reduction of one time unit to two time units. The A-C-E-F path remains critical at 11 time units and direct costs go up to $1,050 since it cost $50 to crash A.

2

1

C

E

4

4

Crash Round 2

B

D

What was crashed:

(Enter response)

Adjusted total direct cost:

(Enter response)

A

F

C

E

Crash Round 3

B

D

What was crashed:

(Enter response)

Adjusted total direct cost:

(Enter response)

A

F

C

E

Crash Round 4

B

D

What was crashed:

(Enter response)

Adjusted total direct cost:

(Enter response)

A

F

C

E

Ch 9 Ex 2

PMT472 3.2 ASSIGNMENT: WEEK 3 EXERCISES

CH. 9 EXERCISE 2

Use the following information contained below to compress one time unit per move using the least-cost method.* Reduce the schedule until you reach the crash point of the network. For each move identify what activity or activities were crashed and the adjusted total direct cost. Note: Choose B instead of C and E (equal costs) because it is usually smarter to crash early rather than late AND one activity instead of two activities.

Activity
Crash Cost (slope)

Maximum Crash Time

Normal Time

Normal Cost

A
$0

2

$150

B
$100

1

3

$100

C
$50

2

6

$200

D
$40

1

4

$200

E
$50

1

3

$200

F
$0

0

1

$150

Crash Round 1

C

What was crashed:

(Enter response)

Adjusted total direct cost:

(Enter response)

A

B

F

D

E

Crash Round 2

C

What was crashed:

(Enter response)

Adjusted total direct cost:

(Enter response)

A

B

F

D

E

Crash Round 3

C

What was crashed:

(Enter response)

Adjusted total direct cost:

(Enter response)

A

B

F

D

E

Ch 9 Ex 3

PMT472 3.2 ASSIGNMENT: WEEK 3 EXERCISES

CH. 9 EXERCISE 3

Use the following information to compress one time unit per move using the least-cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity or activities were crashed and the adjusted total direct cost.

Activity
Crash Cost (slope)

Maximum Crash Time

Normal Time

Normal Cost

A
$100

1

2

$150

B
$80

1

3

$100

C
$60

1

2

$200

D
$40

1

5

$200

E
$40

2

5

$200

F
$40

2

3

$150

G
$20

1

5

$200

H
$0

0

1

$200

Crash Round 1

C

F

What was crashed:

(Enter response)

B

Adjusted total direct cost:

(Enter response)

A

H

D

G

E

Crash Round 2

C

F

What was crashed:

(Enter response)

B

Adjusted total direct cost:

(Enter response)

A

H

D

G

E

Crash Round 3

C

F

What was crashed:

(Enter response)

B

Adjusted total direct cost:

(Enter response)

A

H

D

G

E

Crash Round 4

C

F

What was crashed:

(Enter response)

B

Adjusted total direct cost:

(Enter response)

A

H

D

G

E

Ch 9 Ex 4

PMT472 3.2 ASSIGNMENT: WEEK 3 EXERCISES

CH. 9 EXERCISE 4

Given the data and information that follow, compute the total direct cost for each project duration. If the indirect costs for each project duration are $90 (15 time units), $70 (14), $50 (13), $40 (12), and $30 (11), compute the total project cost for each duration.

NOTE: Total project cost = total direct cost + indirect cost.

Activity
Crash Cost (slope)

Maximum Crash Time

Normal Time

Normal Cost

A
$30

1

5

$50

B
$60

2

3

$60

C
$0

0

4

$70

D
$10

1

2

$50

E
$60

3

5

$100

F
$100

1

2

$90

G
$30

1

5

$50

H
$0

0

2

$60

I
$200

1

3

$200

Crash Round 1

C

F

What was crashed:

(Enter response)

A

Adjusted total direct cost:

(Enter response)

Indirect cost (given):

(Enter response)

D

G

I

Adjusted total project cost:

(Enter response)

B

E

H

Crash Round 2

C

F

What was crashed:

(Enter response)

A

Adjusted total direct cost:

(Enter response)

Indirect cost (given):

(Enter response)

D

G

I

Adjusted total project cost:

(Enter response)

B

E

H

Crash Round 3

C

F

What was crashed:

(Enter response)

A

Adjusted total direct cost:

(Enter response)

Indirect cost (given):

(Enter response)

D

G

I

Adjusted total project cost:

(Enter response)

B

E

H

Crash Round 4

C

F

What was crashed:

(Enter response)

A

Adjusted total direct cost:

(Enter response)

Indirect cost (given):

(Enter response)

D

G

I

Adjusted total project cost:

(Enter response)

B

E

H

What is the optimum cost-time schedule for the project? What is this cost?

(Enter response)

Ch 9 Ex 5

PMT472 3.2 ASSIGNMENT: WEEK 3 EXERCISES

CH. 9 EXERCISE 5

Use the following information to compress one time unit per move using the least-cost method. Assume the total indirect cost for the project is $700 and there is a savings of $50 per time unit reduced. Record the total direct, indirect, and project costs for each duration.

Activity
Crash Cost (slope)

Maximum Crash Time

Normal Time

Normal Cost

A

0

2

$100

B
$100

1

3

$200

C
$40

1

5

$200

D
$60

2

3

$200

E
$20

1

5

$200

F
$40

1

4

$150

G
$0

0

2

$150

Crash Round 1

B

D

What was crashed:

(Enter response)

Adjusted total direct cost:

(Enter response)

Adjusted total indirect cost:

(Enter response)

A

E

G

Adjusted total project cost:

(Enter response)

C

F

Crash Round 2

B

D

What was crashed:

(Enter response)

Adjusted total direct cost:

(Enter response)

Adjusted total indirect cost:

(Enter response)

A

E

G

Adjusted total project cost:

(Enter response)

C

F

What is the optimum cost-time schedule for the project? What is this cost?

(Enter response)

Ch 9 Ex 6

PMT472 3.2 ASSIGNMENT: WEEK 3 EXERCISES

CH. 9 EXERCISE 6

If the indirect costs for each duration are $300 for 27 days, $240 for 26 days, $180 for 25 days, $120 for 24 days, $60 for 23 days, and $50 for 22 days, compute the direct, indirect, and total costs for each duration.

Activity
Crash Cost (slope)

Maximum Crash Time

Normal Time

Normal Cost

A
$80

2

10

$40

B
$30

3

8

$10

C
$40

1

5

$80

D
$50

2

11

$50

E
$100

4

15

$100

F
$30

1

6

$20

Crash Round 1
A

D

What was crashed:

(Enter response)

Adjusted total direct cost:

(Enter response)

Indirect cost (given):

(Enter response)

B

F

Adjusted total project cost:

(Enter response)

C

E

Crash Round 2
A

D

What was crashed:

(Enter response)

Adjusted total direct cost:

(Enter response)

Indirect cost (given):

(Enter response)

B

F

Adjusted total project cost:

(Enter response)

C

E

Crash Round 3
A

D

What was crashed:

(Enter response)

Adjusted total direct cost:

(Enter response)

Indirect cost (given):

(Enter response)

B

F

Adjusted total project cost:

(Enter response)

C

E

Crash Round 4
A

D

What was crashed:

(Enter response)

Adjusted total direct cost:

(Enter response)

Indirect cost (given):

(Enter response)

B

F

Adjusted total project cost:

(Enter response)

C

E

Crash Round 5
A

D

What was crashed:

(Enter response)

Adjusted total direct cost:

(Enter response)

Indirect cost (given):

(Enter response)

B

F

Adjusted total project cost:

(Enter response)

C

E

What is the optimum cost-time schedule?

(Enter response)

The customer offers you $10 for every day you shorten the project from your original network. Would you take it? If so for how many days?

(Enter response)

Ch 9 Ex 7

PMT472 3.2 ASSIGNMENT: WEEK 3 EXERCISES

CH. 9 EXERCISE 7

Use the following information to compress one time unit per move using the least-cost method. Assume the total indirect cost for the project is $2,000 and there is a savings of $100 per time unit reduced. Calculate the total direct, indirect, and project costs for each duration. Plot these costs on a graph.

Activity
Crash Cost (slope)

Maximum Crash Time

Normal Time

Normal Cost

A
$0

0

2

$200

B
$50

1

4

$1,000

C
$200

2

5

$800

D
$200

2

5

$1,000

E
$100

1

3

$800

F
$40

1

5

$1,000

G
$40

1

4

$1,000

H
$0

0

1

$200

Crash Round 1

C

F

What was crashed:

(Enter response)

Adjusted total direct cost:

(Enter response)

A

B

E

H

Adjusted total indirect cost:

(Enter response)

Adjusted total project cost:

(Enter response)

D

G

Crash Round 2

C

F

What was crashed:

(Enter response)

Adjusted total direct cost:

(Enter response)

A

B

E

H

Adjusted total indirect cost:

(Enter response)

Adjusted total project cost:

(Enter response)

D

G

Crash Round 3

C

F

What was crashed:

(Enter response)

Adjusted total direct cost:

(Enter response)

A

B

E

H

Adjusted total indirect cost:

(Enter response)

Adjusted total project cost:

(Enter response)

D

G

Crash Round 4

C

F

What was crashed:

(Enter response)

Adjusted total direct cost:

(Enter response)

A

B

E

H

Adjusted total indirect cost:

(Enter response)

Adjusted total project cost:

(Enter response)

D

G

Crash Round 5

C

F

What was crashed:

(Enter response)

Adjusted total direct cost:

(Enter response)

A

B

E

H

Adjusted total indirect cost:

(Enter response)

Adjusted total project cost:

(Enter response)

D

G

NOTE: Enter data for the graph in the table below and the graph will automatically update.

Duration
Total Direct Cost

Total Indirect Cost

Total Project Cost

What is the optimum cost-time schedule for the project?

(Enter response)

Total Project Cost Breakdown

Total Direct Cost Total Indirect Cost Total Project Cost

Duration

Cost

Ch 9 Ex 8

PMT472 3.2 ASSIGNMENT: WEEK 3 EXERCISES

CH. 9 EXERCISE 8

Use the following information to compress one time unit per move using the least-cost method.* Reduce the schedule until you reach the crash point of the network. For each move identify what activity or activities were crashed and the adjusted total cost, and explain your choice if you have to choose between activities that cost the same. The indirect cost for each duration is $1,500 for 17 weeks, $1,450 for 16 weeks, $1,400 for 15 weeks, $1,350 for 14 weeks, $1,300 for 13 weeks, and $1,250 for 12 weeks.

Activity
Crash Cost (slope)

Maximum Crash Time

Normal Time

Normal Cost

A
$0

0

3

$150

B
$100

1

4

$200

C
$60

1

3

$250

D
$40

1

4

$200

E
$0

0

2

$250

F
$30

2

3

$200

G
$20

1

2

$250

H
$60

2

4

$300

I
$200

1

2

$200

Crash Round 1

B

F

G

What was crashed:

(Enter response)

Adjusted total direct cost:

(Enter response)

A

D

I

Indirect cost (given):

(Enter response)

Adjusted total project cost:

(Enter response)

C

E

H

Crash Round 2

B

F

G

What was crashed:

(Enter response)

Adjusted total direct cost:

(Enter response)

A

D

I

Indirect cost (given):

(Enter response)

Adjusted total project cost:

(Enter response)

C

E

H

What is the optimum cost-time schedule for the project? What is this cost?

(Enter response)

image1

image2

image3

image4

image5

image6

image7

image8

image9

Calculate the price of your order

Select your paper details and see how much our professional writing services will cost.

We`ll send you the first draft for approval by at
Price: $36
  • Freebies
  • Format
  • Formatting (MLA, APA, Chicago, custom, etc.)
  • Title page & bibliography
  • 24/7 customer support
  • Amendments to your paper when they are needed
  • Chat with your writer
  • 275 word/double-spaced page
  • 12 point Arial/Times New Roman
  • Double, single, and custom spacing
  • We care about originality

    Our custom human-written papers from top essay writers are always free from plagiarism.

  • We protect your privacy

    Your data and payment info stay secured every time you get our help from an essay writer.

  • You control your money

    Your money is safe with us. If your plans change, you can get it sent back to your card.

How it works

  1. 1
    You give us the details
    Complete a brief order form to tell us what kind of paper you need.
  2. 2
    We find you a top writer
    One of the best experts in your discipline starts working on your essay.
  3. 3
    You get the paper done
    Enjoy writing that meets your demands and high academic standards!

Samples from our advanced writers

Check out some essay pieces from our best essay writers before your place an order. They will help you better understand what our service can do for you.

  • Analysis (any type)
    Advantages and Disadvantages of Lowering the Voting Age to Thirteen
    Undergrad. (yrs 1-2)
    Political science
    APA
  • Coursework
    Leadership
    Undergrad. (yrs 1-2)
    Business Studies
    APA
  • Essay (any type)
    Is Pardoning Criminals Acceptable?
    Undergrad. (yrs 1-2)
    Criminal Justice
    MLA

Get your own paper from top experts

Order now

Perks of our essay writing service

We offer more than just hand-crafted papers customized for you. Here are more of our greatest perks.

  • Swift delivery
    Our writing service can deliver your short and urgent papers in just 4 hours!
  • Professional touch
    We find you a pro writer who knows all the ins and outs of your subject.
  • Easy order placing/tracking
    Create a new order and check on its progress at any time in your dashboard.
  • Help with any kind of paper
    Need a PhD thesis, research project, or a two-page essay? For you, we can do it all.
  • Experts in 80+ subjects
    Our pro writers can help you with anything, from nursing to business studies.
  • Calculations and code
    We also do math, write code, and solve problems in 30+ STEM disciplines.

Frequently asked questions

Get instant answers to the questions that students ask most often.

See full FAQ
  • Is there a possibility of plagiarism in my completed order?

    We complete each paper from scratch, and in order to make you feel safe regarding its authenticity, we check our content for plagiarism before its delivery. To do that, we use our in-house software, which can find not only copy-pasted fragments, but even paraphrased pieces of text. Unlike popular plagiarism-detection systems, which are used by most universities (e.g. Turnitin.com), we do not report to any public databases—therefore, such checking is safe.

    We provide a plagiarism-free guarantee that ensures your paper is always checked for its uniqueness. Please note that it is possible for a writing company to guarantee an absence of plagiarism against open Internet sources and a number of certain databases, but there is no technology (except for turnitin.com itself) that could guarantee no plagiarism against all sources that are indexed by turnitin. If you want to be 100% sure of your paper’s originality, we suggest you check it using the WriteCheck service from turnitin.com and send us the report.

  • I received some comments from my teacher. Can you help me with them?

    Yes. You can have a free revision during 7 days after you’ve approved the paper. To apply for a free revision, please press the revision request button on your personal order page. You can also apply for another writer to make a revision of your paper, but in such a case, we can ask you for an additional 12 hours, as we might need some time to find another writer to work on your order.

    After the 7-day period, free revisions become unavailable, and we will be able to propose only the paid option of a minor or major revision of your paper. These options are mentioned on your personal order page.

  • How will I receive a completed paper?

    You will get the first version of your paper in a non-editable PDF format within the deadline. You are welcome to check it and inform us if any changes are needed. If everything is okay, and no amendments are necessary, you can approve the order and download the .doc file. If there are any issues you want to change, you can apply for a free revision and the writer will amend the paper according to your instructions. If there happen to be any problems with downloading your paper, please contact our support team.
  • Where do I upload files?

    When you submit your first order, you get a personal account where you can track all your orders, their statuses, your payments, and discounts. Among other options, you will have a possibility to communicate with your writer via a special messenger. You will be able to upload all information and additional materials on your paper using the “Files” tab on your personal page. Please consider uploading everything you find necessary for our writer to perform at the highest standard.
See full FAQ

Take your studies to the next level with our experienced specialists

Live Chat+1 (857) 777-1210 EmailWhatsApp